change orders

Change orders approved for Howard Commons apartment complex

By Kevin Boneske Staff Writer HOWARD – Change orders totaling nearly $29,000 for the Howard Commons apartment complex were approved Monday, June 22, by the village board. The most expensive of the 14 change orders came to $4,500 for window blind color revision. Located between the YMCA and Meadowbrook Park, the Howard Commons was designed …

Change orders approved for Howard Commons apartment complex Read More »

apartment complex

Bids approved for third Howard Commons building

By Kevin Boneske Staff Writer HOWARD – Construction bids and allowances totaling $9,198,109 to construct the third building of the Howard Commons apartment complex were approved Monday, Feb. 25, by the Howard village board. The 45-unit apartment building is scheduled to be completed in the spring of 2020 after beginning construction this coming spring. When …

Bids approved for third Howard Commons building Read More »